May 21 update
Last week, Interwest Construction Inc. (ICI) continued the excavation work at the east side of the Canyon Creek site, MP 10.5. This work included excavation of the slope and ditch-line, as well as milling a portion of the existing asphalt in the north lane, to establish the slight shift in the new alignment of the roadway. ICI continued preparing the foundation areas of the Canyon Creek bridge, ahead of the pile driving work to be completed the first week of June.
This week, ICI will continue this excavation and slope shaping work at Canyon Creek and will begin installing the erosion control matting on the finished slopes.
Project Website: highways.dot.gov/federal-lands/projects/wa/jeff-91420-1
Impacts to Traffic:
• Temporary traffic control signals and/or flaggers can be expected at all times at Canyon Creek, MP 10.5.
• Expect delays up to 30 minutes through the project limits (MP 3 through MP 11) between 8 a.m. and 5 p.m., weekdays, and minor delays at the traffic signals outside of these hours.
• Olympic National Park and businesses along Upper Hoh River Road will remain accessible at all times during construction.